400MW Richards Bay Gas Power Facility, KwaZulu-Natal

Amendment Process

Richards Bay Gas Power 2 (Pty) Ltd (the Applicant) has requested an amendment to the existing Environmental Authorisation (EA) for the authorised development of the 400MW Richards Bay Gas to Power Facility, located within Zone 1F of the Richards Bay Industrial Development Zone (IDZ) in Richards Bay, KwaZulu-Natal Province. An amendment application, final EMPr and Layout approval processes is being undertaken. Motivation Report is available for a 30-day review. Review period: 23 July 2026 to 24 August 2026. Register your interest to become involved in the amendment process. Bhalisa usho isasasa lakho ukuze ube yingxenye yale nqubo. Registreer u belangstelling om by die wysigingsproses betrokke te raak.

Zone 1F Richards Bay IDZ, Richards Bay
Invitation to Register
Gas to Power
May 2026
Banken Wind Energy Facility Cluster, Northern Cape

Scoping & EIA

Banken Wind Energy Facility 1 (Pty) Ltd proposes development of a wind energy facility and associated infrastructure ~25km south of Aggeneys in the Northern Cape Province. The wind farm is to be known as the Banken Wind Energy Facility 1. Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak.

~25km south of Aggeneys, Khâi-Ma Local Municipality, Northern Cape
Invitation to Register
Renewable Energy
July 2026
Bloukrans Solar PV Facility

Scoping & EIA

Eden Renewables South Africa (Pty) Ltd proposes to establish the Bloukrans Solar PV Project comprising two co-located solar photovoltaic (PV) facilities (Bloukrans Solar PV1 and Bloukrans Solar PV2) with a total generating capacity of up to 475MW (~237MW each), and a co-located Battery Energy Storage System (BESS) of up to 200MWh, to supply renewable energy to the national grid. Revised EIA Report is available for a 30-day review. Review period: 14 September 2026 to 14 October 2026. Register your interest to become involved in the process. Bhalisa usho isasasa lakho ukuze ube yingxenye yale nqubo. Registreer u belangstelling om by die proses betrokke te raak.

~9.2km southwest of Colenso and ~20km northeast of Estcourt in KwaZulu-Natal Province.
Report for Comment
Renewable Energy
July 2026
Calodex Solar PV Facility, Gauteng

Amendment

Calodex (Pty) Ltd has requested an amendment for the authorised development of the 115MW Calodex Solar Photovoltaic (PV) Facility on a site approximately 5km north of Springs in the Gauteng Province. An amendment application, final EMPr and Layout approval processes is being undertaken. Motivation Report is available for a 30-day review. Review period: 17 July 2026 to 18 August 2026. Register your interest to become involved in the amendment process. Registreer u belangstelling om by die wysigingsproses betrokke te raak.

Located north of Enstra Paper, near Springs in the City of Ekurhuleni, Gauteng
Motivation Report for Comment
Renewable Energy
July 2026
Elangeni Solar PV Facility

Scoping & EIA

JUWI Renewable Energies (Pty) Ltd proposes the development of the Elangeni Solar Photovoltaic (PV) and electricity grid infrastructure (EGI) Project and associated infrastructure with an installed capacity of up to ~130MWp and a contracted capacity of up to ~100MWac, including a Battery Energy Storage System (BESS) and associated grid connection infrastructure.

The project is situated on the farm Moordspruit No. 856 GS, near Frere, KwaZulu Natal Province
Final Scoping Report
Renewable Energy
March 2026
Ga-Machacha Solar PV Cluster and Associated Infrastructure, Limpopo

Scoping & EIA

The development of a solar PV cluster comprising four separate solar photovoltaic (PV) facilities and associated infrastructure, with a total generating capacity of up to 900MW. The details and development areas for the 4 solar PV facilities include: • Ga-Machacha Solar PV 1: Capacity of 240MW with a development area up to 301ha (Portion 0 of the Farm Scheepersrust 771 KS) • Ga-Machacha Solar PV 2: Capacity of 240MW with a development area up to 325ha (Portion 0 of the Farm Scheepersrust 771 KS) • Ga-Machacha Solar PV 3: Capacity of 240MW with a development area up to 320ha (Portion 0 of the Farm Scheepersrust 771 KS) • Ga-Machacha Solar PV 4: Capacity of 180MW with a development area up to 223ha (Portion 0 of the Farm Scheepersrust 771 KS) EIA Report is available for 30-day review. Review period: 25 September 2026 to 26 October 2026. Register your interest to become involved in the process. Ngwadiša kgahlego ya gago ya go kgatha tema ka tshepedišong.

~11km south of Ga-Nkoana and 20km north-west of Jane Furse, within the Tubatse Fetakgomo Local Municipality and the Sekhukhune District Municipality
Report for Comment
Renewable Energy
Garden Route Gas to Power Project

Scoping and EIA

Gourikwa Route Power Development (Pty) Ltd proposes the development of a combined-cycle gas turbine (CCGT) power plant of up to 3 000 MW, together with associated electrical grid connection infrastructure, gas receiving and auxiliary fuel infrastructure, water supply infrastructure, and associated ancillary infrastructure. It is proposed that the facility will utilise indigenous natural gas sourced from Block 11B/12B, southwest of Mossel Bay, or an alternative gas and/or other fuel source/s, and/or fuel stored on site in storage tanks. **Notice: postponement of the review period and public open day** Gourikwa Route Power Development (Pty) Ltd, together with Savannah Environmental, wishes to advise that the 30-day review and comment period for the Scoping Report for the proposed Garden Route Gas to Power Project and associated infrastructure, Mossel Bay, Western Cape Province, has been unavoidably postponed pending the finalisation of outstanding project information required to support the Scoping and EIA process. Live Read Radio notices issued on 18 September 2026, and newspaper adverts published on 25 September 2026, indicated that the Scoping Report would be available for review and comment from Monday, 28 September 2026. The report will not be made available for that review and comment period. The public open day scheduled for Tuesday, 13 October 2026, 15:00–19:00, at D’Almeida Community Hall, Mossel Bay, is postponed. A new date for the release of the Scoping Report, and a new date for the public open day, will be announced through the same notification methods, including direct notification to registered Interested and Affected Parties. Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak. Bhalisa usho isasasa lakho ukuze ube yingxenye yale nqubo.

The project will traverse various properties, ~14km west of Mossel Bay in Western Cape Province.
Review period postponed
Gas to Power
November 2025
Holy Land Development, Gauteng

S24G Application

Impact for Christ Ministries is applying under Section 24G of NEMA for rectification of unlawful activities on Portion 35 of the Farm Tweefontein 523 JQ, located within the Cradle of Humankind World Heritage Site. The Final Report has been submitted to the Gauteng Department of Agriculture and Rural Development (GDARD). Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak. Ngwadiša kgahlego ya gago ya go kgatha tema ka tshepedišong.

~20km north-east of Krugersdorp and 7km north-west of Lanseria Airport, Mogale City Local Municipality, Gauteng
Final Report
Accommodation
May 2026
Kalgold Solar PV Facility, North West

Basic Assessment

Kalgold Solar PV (Pty) Ltd, together with Harmony Gold Mining Company Limited (Harmony Gold) is looking to supplement the Harmony Kalgold Mine operations (the Mine) energy supply by implementing solar PV generation technology at their site, aiding their transition to a more sustainable and environmentally friendly energy mix. The development of the Kalgold Solar PV facility with a generating capacity of up to 19.5MW is proposed east of the Harmony Kalgold operations The Basic Assessment Report has been updated, as applicable, and submitted to the North West Department of Economic Development, Environment, Conservation and Tourism for decision-making.

~14km north west of Kraaipan and ~19km north east from Setlagole, Ratlou Rand Local Municipality, North West
Final BA Report
Renewable Energy
June 2026
Khanyisa Solar PV Facility Expansion, Gauteng

Scoping & EIA

South Deep Joint Venture proposes to expand the existing Khanyisa Solar PV facility by an additional 30MW. This expansion will increase the total generation capacity up to 80MW. To support the additional capacity, the project will utilise electrical grid infrastructure that will connect the expanded facility to the Twin Shaft Substation by looping into the existing 11 kV underground transmission line situated approximately 250m east of the operational solar plant. The Final Scoping Report has been finalised and submitted to the Gauteng Department of Environment (GDEnv).

~7km from Westonaria within the West Rand Local Municipality
Final Scoping Report
Renewable Energy
June 2026
Lichtenburg 3 PV Solar Facilities, North-west Province

Amendment of EMPr

ABO Wind Lichtenburg 3 PV (Pty) Ltd propose to amend the approved Environmental Management Programmes (EMPrs) for the operational Lichtenburg 1, 2 and 3 PV Solar Facilities (DFFE Refs: 14/12/16/3/3//1093, issued July 2019) to allow herbicide use as an alternative for effective vegetation control during construction and/or operational phases. This supports ongoing maintenance, fire risk management, and site safety while the facilities remain operational. Amended EMPrs is available for a 30-day review. Review period: 15 June 2026 to 16 July 2026. Register your interest to become involved in the process. Bhalisa usho isasasa lakho ukuze ube yingxenye yale nqubo. Registreer u belangstelling om by die proses betrokke te raak.

Near Lichtenburg, North-West Province
Draft EMPr Report
Renewable Energy
January 2026
Matsheng Solar PV Cluster and Associated Infrastructure, North West Province

Scoping & EIA

Matsheng Solar PV (RF)(Pty) Ltd proposes the development of a solar PV cluster with a total generating capacity of approximately 1920MW, comprising four separate solar photovoltaic (PV) facilities and associated infrastructure. The Background Information Document, providing details of the project and how to become involved in the process is available for download below. Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak. Kwadisa kgatlhegelo ya gago gore o nne le seabe mo tiragalong e.

~17km southeast of Hartswater and approximately 7km southeast of Manthestad, within the Greater Taung Local Municipality and Dr Ruth Segomotsi Mompati District Municipality
Invitation to Register
Renewable Energy
August 2026
Merafong Hybrid Park 2 and Associated Infrastructure, Gauteng Province

Scoping & EIA

Solani Renewables Proprietary (Pty) Ltd proposes the development of the Merafong Hybrid Facility 2, comprising a hybrid renewable energy facility with a contracted generation capacity of up to 175MW and a 600MWh Battery Energy Storage System (BESS). Final Scoping Report has been finalised and submitted to the Department of Forestry, Fisheries and the Environment (DFFE) Register your interest to become involved in the process. Bhalisa umdla wakho wokuthatha inxaxheba kwinkqubo. Registreer u belangstelling om by die proses betrokke te raak. Ngolisa thahasello ea hau ea ho nka karolo ts'ebetsong ena.

~12km east of the town of Carletonville, within the Merafong City Local Municipality, Gauteng Province
Final Scoping Report
Renewable Energy
January 2026
Morokweni Solar PV Cluster and Associated Infrastructure, North West Province

Scoping & EIA

Morokweni Solar PV (RF) (Pty) Ltd proposes the development of a cluster of solar PV facilities with a total generation capacity of up to ~3360MW. Each facility will have a capacity of up to 480MW. The Background Information Document, providing details of the project and how to become involved in the process is available for download below. Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak. Kwadisa kgatlhegelo ya gago gore o nne le seabe mo tiragalong e.

~12km south-east of Taung and ~3km south of Manthestad, Greater Taung Local Municipality, Dr Ruth Segomotsi Mompati District Municipality
Invitation to Register
Renewable Energy
September 2026
Mponeng Solar PV Facility

Scoping and Environmental Impact Assessment

Mponeng Solar PV (Pty) Ltd (the Applicant) proposes the development of a solar photovoltaic (PV) facility with a generating capacity of up to 140 MW, including a Battery Energy Storage System (BESS) with a capacity of up to 200 MWh, and associated infrastructure (including a 66 kV overhead power line to the Deep Levels South 132 kV Substation). The power generated will be used to supplement Harmony Gold Mining Company Ltd’s energy supply at the Mponeng Gold Mine.

Approximately 6 km southeast of Carletonville and 6 km north of Fochville, Gauteng Province
Final Scoping Report
Renewable Energy
August 2026
Naudesbank Solar PV Facility, Mpumalanga

Basic Assessment

NDB PV (Pty) Ltd (the Applicant), a Special Purpose Vehicle (SPV), proposes to develop the Naudesbank Solar Farm, a ground-mounted solar photovoltaic (PV) facility and associated infrastructure intended to support the electricity requirements of the existing Naudesbank mining operation. BA Report is available for a 30-day review. Review period: 06 August 2026 to 07 September 2026 Register your interest to become involved in the process. Bhalisa usho isasasa lakho ukuze ube yingxenye yale nqubo. Registreer u belangstelling om by die proses betrokke te raak.

Between the towns of Hendrina and Carolina, Mpumalanga Province
Report for Comment
Renewable Energy
July 2025
Phakwe Richards Bay Gas Power 3 (PRBGP3) Grid Connection Infrastructure, KwaZulu-Natal

Basic Assessment

Phakwe Richards Bay Gas Power 3 (Pty) Ltd proposes the construction and operation of grid connection infrastructure consisting of a new 400kV Main Transmission Substation and 4×400kV overhead power lines to connect the authorised 2000MW gas to power facility to the national grid. The Background Information Document, providing details of the project and how to become involved in the process is available for download below. Register your interest to become involved in the process. Bhalisa usho isasasa lakho ukuze ube yingxenye yale nqubo. Registreer u belangstelling om by die proses betrokke te raak.

~3km east of Richards Bay and ~2km southwest of Empangeni, City of uMhlathuze Local Municipality, KwaZulu-Natal
Invitation to Register
Grid Infrastructure
Phefumula Emoyeni One Grid Connection, Mpumalanga

Scoping & EIA

Phefumula Emoyeni One (Pty) Ltd proposes the construction and operation of grid connection infrastructure to connect the authorised Phefumula Emoyeni One Wind Energy Facility (WEF) (DFFE Ref.: 14/12/16/3/3/2/2696) to the national grid. The proposed grid connection infrastructure is located approximately 16 km north of Ermelo, within the Msukaligwa Local Municipality and Gert Sibande District Municipality, Mpumalanga Province. Background Information documents available for perusal. Scoping Report is available for a 30-day review period. Review period: 14 September 2026 to 15 October 2026. Register your interest to become involved in the process. Bhalisa usho isasasa lakho ukuze ube yingxenye yale nqubo. Registreer u belangstelling om by die proses betrokke te raak.

~16km north of Ermelo, Msukaligwa Local Municipality, Gert Sibande District Municipality, Mpumalanga Province
Scoping Report for Comment
Renewable Energy
August 2026
Sleeping Giant MTS, Eastern Cape

Basic Assessment

FE Sleeping Giant (Pty) Ltd proposes to develop the Sleeping Giant Main Transmission Substation (MTS) within the authorised FE Kudu Wind Energy Facility development area. The MTS will comprise both a 132kV/400kV and a 400kV/765kV step-up transformer(s) bay(s) to evacuate generated electricity to the authorised Eskom Gamma-Grassridge 765kV power line via a future loop-in-loop-out (LILO) connection. Basic Assessment Report is available for a 30-day review. Review period: 03 August 2026 to 04 September 2026. Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak.

Located approximately 40km west of the town of Xamdeboo (formerly Aberdeen), Dr Beyers Naudé Local Municipality, Eastern Cape
Basic Assessment Report for Review
Grid Infrastructure
February 2026
ST2 Springbok ilanga Solar PV including BESS and Associated Grid Connection Infrastructure, Northern Cape

Basic Assessment

ST2 Abangani (Pty) Ltd proposes the development of a solar photovoltaic (PV) facility and associated infrastructure, including battery energy storage systems (BESS) and grid connection infrastructure. The Basic Assessment Report has been finalised and submitted to the Department of Forestry, Fisheries and the Environment (DFFE). Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak. Kwadisa kgatlhegelo ya gago gore o nne le seabe mo tiragalong e.

~38 km north-east of Concordia and 56km south-west of Aggeneys, Nama Khoi Local Municipality within the Namakwa District Municipality
Decision Received
Renewable Energy
June 2026
Ummbila Emoyeni Five Wind Energy Facility, Mpumalanga

Scoping & EIA

Ummbila Emoyeni Five (Pty) Ltd is proposing the development of the Ummbila Emoyeni Five Wind Energy Facility (WEF) on a site in the Mpumalanga Province. Eleven turbines were previously authorised as part of the original Ummbila Emoyeni WEF (EIA Ref 14/12/16/3/3/2/2160/5) while the current application allowed for the development of a further 11 turbines with associated grid infrastructure. The project is located approximately 8km east of Morgenzon, within the Lekwa Local Municipality, Gert Sibande District Municipality in the Mpumalanga Province. The DFFE has granted Environmental Authorisation. The Appeal Period is ending on 26 October 2026.

Morgenzon, Lekwa Local Municipality within the Gert Sibande District Municipality
Decision received
Renewable Energy
May 2026
Ummbila Emoyeni Four Wind Energy Facility, Mpumalanga

Amendment

Ummbila Emoyeni Cluster (Pty) Ltd is proposing amendments to the approved Ummbila Emoyeni Four Wind Energy Facility (WEF), with a contracted capacity of up to 140MW, and associated grid connection infrastructure on a site near Morgenzon in the Lekwa Local Municipality within the greater Gert Sibande District Municipality, Mpumalanga. The project forms part of the greater Ummbila Emoyeni WEF authorised under the Department of Forestry, Fisheries and the Environment (DFFE) (Ref. No. 14/12/16/3/3/2/2160). The Revised EMPr and Layout is available for a 30-day review and comment period. Register your interest to become involved in the process.

Morgenzon, Lekwa Local Municipality within the Gert Sibande District Municipality
Final EMPrs & Layout
Renewable Energy
August 2026
Ummbila Emoyeni Solar Energy Facility, Mpumalanga

Amendment Process

Emoyeni Renewable Energy Farm (Pty) Ltd has requested an amendment for the authorised development of the Ummbila Emoyeni Solar PV Facility on a site approximately 6km southeast of Bethal and approximately 1km east of Morgenzon within the Govan Mbeki & Lekwa Local Municipalities, Gert Sibande District Municipality, Mpumalanga. An amendment application for the Final EMPrs and Final Layout approval processes is being undertaken. Final Environmental Management Programmes (EMPrs) and Final Layout are available for a 30-day review. Review period: 28 August 2026 to 28 September 2026. Register your interest to become involved in the amendment process. Bhalisa usho isasasa lakho ukuze ube yingxenye yale nqubo. Registreer u belangstelling om by die wysigingsproses betrokke te raak.

Located near the town of Bethal and Morgenzon, within the Govan Mbeki & Lekwa Local Municipalities, Gert Sibande District Municipality, Mpumalanga
Final EMPrs & Final Layout for Comment
Renewable Energy
Vhembe Solar PV and Associated Infrastructure, Limpopo Province

Scoping & EIA

The Applicant, JUWI Renewable Energies (Pty) Ltd, is proposing the construction and operation of a Photovoltaic (PV) Solar Energy Facility and associated infrastructure (also referred to herein as 'the Project'). The facility will have a contracted capacity of up to 480MW and will be known as Vhembe Solar PV and Associated Infrastructure. The power will be evacuated by a Loop-in Loop-out (LILO) connection into the 132 kV Venetia–Njelele overhead line that traverses the project site. The Scoping Report is available for a 30-day review period. Review period: 09 October 2026 to 9 November 2026 Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak. Ngwadiša kgahlego ya gago gore o tšee karolo tshepedišong yeo. Kha vha ṅwalise dzangalelo ḓavho uri vha dzhenele kha maitele.

~~50km south west of the town of Musina and 49km north east of the town of Alldays, Limpopo Province.
Report for Comment
Renewable Energy