July 2026
400MW Richards Bay Gas Power Facility, KwaZulu-Natal

Amendment Process

Richards Bay Gas Power 2 (Pty) Ltd (the Applicant) has requested an amendment to the existing Environmental Authorisation (EA) for the authorised development of the 400MW Richards Bay Gas to Power Facility, located within Zone 1F of the Richards Bay Industrial Development Zone (IDZ) in Richards Bay, KwaZulu-Natal Province. An amendment application, final EMPr and Layout approval processes is being undertaken. Motivation Report is available for a 30-day review. Review period: 23 July 2026 to 24 August 2026. Register your interest to become involved in the amendment process. Bhalisa usho isasasa lakho ukuze ube yingxenye yale nqubo. Registreer u belangstelling om by die wysigingsproses betrokke te raak.

Zone 1F Richards Bay IDZ, Richards Bay
Invitation to Register
Gas to Power
May 2026
Banken Wind Energy Facility Cluster, Northern Cape

Basic Assessment and Scoping & EIA

Banken Wind Energy Facility 1 (Pty) Ltd and Banken Wind Energy Facility 2 (Pty) Ltd proposes development of two separate wind energy facilities and associated infrastructure ~25km south of Aggeneys in the Northern Cape Province. The two wind farms are to be known as the Banken Wind Energy Facility 1 and Banken Wind Energy Facility 2, and form the Banken Wind Energy Facility Cluster. Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak.

~25km south of Aggeneys, Khâi-Ma Local Municipality, Northern Cape
Invitation to Register
Renewable Energy
July 2026
Bloukrans Solar PV Facility

Scoping & EIA

Eden Renewables South Africa (Pty) Ltd proposes to establish the Bloukrans Solar PV Project comprising two co-located solar photovoltaic (PV) facilities (Bloukrans Solar PV1 and Bloukrans Solar PV2) with a total generating capacity of up to 475MW (~237MW each), and a co-located Battery Energy Storage System (BESS) of up to 200MWh, to supply renewable energy to the national grid. The EIA Reports for the Bloukrans Solar PV1 and PV 2 projects is available for your review and comment from Friday, 17 July 2026 to Tuesday, 18 August 2026. The final day to submit comment is Tuesday, 18 August. Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak. Bhalisa usho isasasa lakho ukuze ube yingxenye yale nqubo.

~9.2km southwest of Colenso and ~20km northeast of Estcourt in KwaZulu-Natal Province.
Report for Comment
Renewable Energy
July 2026
Calodex Solar PV Facility, Gauteng

Amendment

Calodex (Pty) Ltd has requested an amendment for the authorised development of the 115MW Calodex Solar Photovoltaic (PV) Facility on a site approximately 5km north of Springs in the Gauteng Province. An amendment application, final EMPr and Layout approval processes is being undertaken. Motivation Report is available for a 30-day review. Review period: 17 July 2026 to 18 August 2026. Register your interest to become involved in the amendment process. Registreer u belangstelling om by die wysigingsproses betrokke te raak.

Located north of Enstra Paper, near Springs in the City of Ekurhuleni, Gauteng
Motivation Report for Comment
Renewable Energy
July 2026
Elangeni Solar PV Facility, KwaZulu-Natal

Scoping & EIA

JUWI Renewable Energies (Pty) Ltd (the Applicant) proposes the development of a solar photovoltaic (PV) facility and associated grid connection infrastructure. The project, known as the Elangeni Solar PV Project, will have an installed capacity of up to ~150MWp. The Scoping Report will be made is available for a 30-day review and comment period from Friday, 31 July 2026 to Tuesday, 01 September 2026. The final day to submit comments is Tuesday, 01 September 2026. Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak. Bhalisa usho isasasa lakho ukuze ube yingxenye yale nqubo.

The project is situated on the farm Moordspruit No. 856 GS, near Frere, KwaZulu-Natal Province
Report for Comment
Renewable Energy
March 2026
Ga-Machacha Solar PV Cluster and Associated Infrastructure, Limpopo

Scoping & EIA

The development of a solar PV cluster comprising four separate solar photovoltaic (PV) facilities and associated infrastructure, with a total generation capacity of up to 900MW. The details and development areas for the 4 solar PV facilities include: • Ga-Machacha Solar PV 1: Capacity of 240MW with a development area up to 301ha (Portion 0 of the Farm Scheepersrust 771 KS) • Ga-Machacha Solar PV 2: Capacity of 240MW with a development area up to 325ha (Portion 0 of the Farm Scheepersrust 771 KS) • Ga-Machacha Solar PV 3: Capacity of 240MW with a development area up to 320ha (Portion 0 of the Farm Scheepersrust 771 KS) • Ga-Machacha Solar PV 4: Capacity of 180MW with a development area up to 223ha (Portion 0 of the Farm Scheepersrust 771 KS) The EIA Report is available for a 30-day review period. Review period: 06 March 2026 to 09 April 2026. Register your interest to become involved in the process. Ngwadiša kgahlego ya gago ya go kgatha tema ka tshepedišong.

~11km south of Ga-Nkoana and 20km north-west of Jane Furse, within the Tubatse Fetakgomo Local Municipality and the Sekhukhune District Municipality
Report for Comment
Renewable Energy
November 2025
Holy Land Development, Gauteng

S24G Application

Impact for Christ Ministries is applying under Section 24G of NEMA for rectification of unlawful activities on Portion 35 of the Farm Tweefontein 523 JQ, located within the Cradle of Humankind World Heritage Site. The Final Report has been submitted to the Gauteng Department of Agriculture and Rural Development (GDARD). Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak. Ngwadiša kgahlego ya gago ya go kgatha tema ka tshepedišong.

~20km north-east of Krugersdorp and 7km north-west of Lanseria Airport, Mogale City Local Municipality, Gauteng
Final Report
Accommodation
May 2026
Kalgold Solar PV Facility, North West

Basic Assessment

Kalgold Solar PV (Pty) Ltd, together with Harmony Gold Mining Company Limited (Harmony Gold) is looking to supplement the Harmony Kalgold Mine operations (the Mine) energy supply by implementing solar PV generation technology at their site, aiding their transition to a more sustainable and environmentally friendly energy mix. The development of the Kalgold Solar PV facility with a generating capacity of up to 19.5MW is proposed east of the Harmony Kalgold operations The Basic Assessment Report has been updated, as applicable, and submitted to the North West Department of Economic Development, Environment, Conservation and Tourism for decision-making.

~14km north west of Kraaipan and ~19km north east from Setlagole, Ratlou Rand Local Municipality, North West
Final BA Report
Renewable Energy
June 2026
Khanyisa Solar PV Facility Expansion, Gauteng

Scoping & EIA

South Deep Joint Venture proposes to expand the existing Khanyisa Solar PV facility by an additional 30MW. This expansion will increase the total generation capacity up to 80MW. To support the additional capacity, the project will utilise electrical grid infrastructure that will connect the expanded facility to the Twin Shaft Substation by looping into the existing 11 kV underground transmission line situated approximately 250m east of the operational solar plant. The Scoping & EIA Report was made available for a 30-day review period from Tuesday, 09 June 2026 to Friday, 10 July 2026. Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak. Bhalisa usho isasasa lakho ukuze ube yingxenye yale nqubo.

~7km from Westonaria within the West Rand Local Municipality
Report for Comment
Renewable Energy
June 2026
Lichtenburg 3 PV Solar Facilities, North-west Province

Amendment of EMPr

ABO Wind Lichtenburg 3 PV (Pty) Ltd propose to amend the approved Environmental Management Programmes (EMPrs) for the operational Lichtenburg 1, 2 and 3 PV Solar Facilities (DFFE Refs: 14/12/16/3/3//1093, issued July 2019) to allow herbicide use as an alternative for effective vegetation control during construction and/or operational phases. This supports ongoing maintenance, fire risk management, and site safety while the facilities remain operational. The Background Information Document, providing details of the project and how to become involved in the process is available for download below. Due to the use of the incorrect EA reference number in the previous public participation process, a second round of public participation is required. The amended EMPrs and supporting documentation was made available for an initial 30-day public review and comment period from 13 March 2026 to 15 April 2026, and has been made available again for addition 30-day public review and comment period from 15 June 2026 to 16 July 2026. Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak. Bhalisa usho isasasa lakho ukuze ube yingxenye yale nqubo.

Near Lichtenburg, North-West Province
Draft EMPr Report
Renewable Energy
July 2026
Loperberg, Malabar & Spreeukloof (now Loperberg) Wind Energy Facilities

Notification of Appeal Decision

On 25 November 2024 the Chief Director granted amendments to the existing Environmental Authorisations (EAs) for the Malabar, Loperberg and Spreeukloof (now Loperberg) Wind Energy Facilities and associated infrastructure near Sterkstroom, Eastern Cape Province. These amendments included, among others, the splitting of certain authorisations, updates to project descriptions and layouts, and extensions to the validity periods of the authorisations. VulPro subsequently lodged an appeal against these decisions. The appeal process has now been finalised.

The project is situated near Sterkstroom, Eastern Cape Province
Appeal Decision
Renewable Energy
January 2026
Matsheng Solar PV Cluster and Associated Infrastructure, North West Province

Scoping & EIA

Matsheng Solar PV (RF)(Pty) Ltd proposes the development of a solar PV cluster with a total generating capacity of approximately 1920MW, comprising four separate solar photovoltaic (PV) facilities and associated infrastructure. The Background Information Document, providing details of the project and how to become involved in the process is available for download below. Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak. Kwadisa kgatlhegelo ya gago gore o nne le seabe mo tiragalong e.

~17km southeast of Hartswater and approximately 7km southeast of Manthestad, within the Greater Taung Local Municipality and Dr Ruth Segomotsi Mompati District Municipality
Invitation to Register
Renewable Energy
August 2026
Merafong Hybrid Facility 2 and Associated Infrastructure, Gauteng Province

Scoping & EIA

Solani Renewables Proprietary (Pty) Ltd proposes the development of the Merafong Hybrid Facility 2, comprising a hybrid renewable energy facility with a contracted generation capacity of up to 175MW and a 600MWh Battery Energy Storage System (BESS). The EIA Report is available for your review and comment from Thursday, 20 August 2026 to Monday, 21 September 2026. The final day to submit comment is Monday, 21 September 2026. Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak. Bhalisa umdla wakho wokuthatha inxaxheba kwinkqubo. Ngolisa thahasello ea hau ea ho nka karolo ts'ebetsong ena.

~12km east of the town of Carletonville, within the Merafong City Local Municipality, Gauteng Province
Report for Comment
Renewable Energy
March 2026
Mercury Substation Expansion, Free State Province

Basic Assessment

National Transmission Company South Africa (SOC) Ltd proposes to expand the footprint of the existing Mercury Main Transmission Substation (MTS) by approximately 5ha. This expansion will accommodate the installation of the first 2000 MVA 765 kV/400 kV transformer (project known as 'Mercury 2000 MVA 765/400 kV Transformer 1'), extension of the 765 kV busbar, equipping of 1x 400 kV and 1x 765 kV transformer bays, installation of 132 kV Fault Current Limiting Reactors (FCLRs), and construction of a laydown area. The Basic Assessment Report has been finalised and submitted to the Department of Forestry, Fisheries and the Environment (DFFE).

Portions 2 and 3 of the Farm Zaaiplaats 190, approximately 9 km south of the town of Orkney, within the Moqhaka Local Municipality, Free State Province
Final Report
Grid Infrastructure
May 2026
Middlevlei Solar Grid Connection Infrastructure, Gauteng

Amendment

Middelvlei Solar (Pty) Ltd is proposing an amendment to the existing Environmental Authorisation (EA) for the construction and operation of the Middelvlei Solar Grid Connection Infrastructure. The facility is located approximately 7 km south-west of the town of Randfontein, within the Rand West City Local Municipality, Gauteng Province. The Motivation Report has been finalised and submitted to the Gauteng Department of Environment (GDEVn). - Register your interest to become involved in the process. - Registreer u belangstelling om by die proses betrokke te raak. - Ngwadiša kgahlego ya gago ya go kgatha tema ka tshepedišong.

~7 km south-west of the town of Randfontein, within the Rand West City Local Municipality, Gauteng Province
Final Report
Grid Infrastructure
January 2026
Morokweni Solar PV Cluster and Associated Infrastructure, North West Province

Scoping & EIA

Morokweni Solar PV (RF) (Pty) Ltd proposes the development of a cluster of solar PV facilities with a total generation capacity of up to ~3360MW. Each facility will have a capacity of up to 480MW. The Background Information Document, providing details of the project and how to become involved in the process is available for download below. Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak. Kwadisa kgatlhegelo ya gago gore o nne le seabe mo tiragalong e.

~12km south-east of Taung and ~3km south of Manthestad, Greater Taung Local Municipality, Dr Ruth Segomotsi Mompati District Municipality
Invitation to Register
Renewable Energy
July 2026
Mponeng Solar PV Facility, Gauteng

Scoping and Environmental Impact Assessment

Mponeng Solar PV (Pty) Ltd (the Applicant) proposes the development of a solar photovoltaic (PV) facility with a generating capacity of up to 140 MW, including a Battery Energy Storage System (BESS) with a capacity of up to 200 MWh, and associated infrastructure (including a 66 kV overhead power line to the Deep Levels South 132 kV Substation). The power generated will be used to supplement Harmony Gold Mining Company Ltd's energy supply at the Mponeng Gold Mine. As a registered Interested and Affected Party (I&AP), you are hereby notified that the Scoping Report and Appendices will be available for your review and comment from Friday, 7 August 2026 to Tuesday, 8 September 2026. The final day to submit comments is Tuesday, 8 September 2026. Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak.

Approximately 6 km southeast of Carletonville and 6 km north of Fochville, Gauteng Province
Report for Comment
Renewable Energy
August 2026
Naudesbank Solar PV Facility, Mpumalanga

Basic Assessment

NDB PV (Pty) Ltd (the Applicant), a Special Purpose Vehicle (SPV), proposes to develop the Naudesbank Solar Farm, a ground-mounted solar photovoltaic (PV) facility and associated infrastructure intended to support the electricity requirements of the existing Naudesbank mining operation. As a registered Interested and Affected Party (I&AP), you are hereby notified that the BA Report will be available for your review and comment from Thursday, 06 August 2026 to Monday, 07 September 2026. The final day to submit comments is Monday, 07 September 2026. Please note that an advertisement published in the Highvelder newspaper indicated that the BA Report would be available from 31 July 2026. Due to unforeseen circumstances, the release of the BA Report has been delayed. Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak. Bhalisa usho isasasa lakho ukuze ube yingxenye yale nqubo.

Between the towns of Hendrina and Carolina, Mpumalanga Province
Report for Comment
Renewable Energy
July 2025
Phakwe Richards Bay Gas Power 3 (PRBGP3) Grid Connection Infrastructure, KwaZulu-Natal

Basic Assessment

Phakwe Richards Bay Gas Power 3 (Pty) Ltd proposes the construction and operation of grid connection infrastructure consisting of a new 400kV Main Transmission Substation and 4×400kV overhead power lines to connect the authorised 2000MW gas to power facility to the national grid. The Background Information Document, providing details of the project and how to become involved in the process is available for download below. Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak. Bhalisa usho isasasa lakho ukuze ube yingxenye yale nqubo.

~3km east of Richards Bay and ~2km southwest of Empangeni, City of uMhlathuze Local Municipality, KwaZulu-Natal
Invitation to Register
Grid Infrastructure
August 2026
Sleeping Giant MTS, Eastern Cape

Basic Assessment

FE Sleeping Giant (Pty) Ltd proposes to develop the Sleeping Giant Main Transmission Substation (MTS) within the authorised FE Kudu Wind Energy Facility development area. The MTS will comprise both a 132kV/400kV and a 400kV/765kV step-up transformer(s) bay(s) to evacuate generated electricity to the authorised Eskom Gamma-Grassridge 765kV power line via a future loop-in-loop-out (LILO) connection. Basic Assessment Report is available for a 30-day review. Review period: 03 August 2026 to 04 September 2026. Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak.

Located approximately 40km west of the town of Xamdeboo (formerly Aberdeen), Dr Beyers Naudé Local Municipality, Eastern Cape
Basic Assessment Report for Review
Grid Infrastructure
February 2026
ST2 Springbok ilanga Solar PV including BESS and Associated Grid Connection Infrastructure, Northern Cape

Basic Assessment

ST2 Abangani (Pty) Ltd proposes the development of a solar photovoltaic (PV) facility and associated infrastructure, including battery energy storage systems (BESS) and grid connection infrastructure. The Basic Assessment Report has been finalised and submitted to the Department of Forestry, Fisheries and the Environment (DFFE). Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak. Kwadisa kgatlhegelo ya gago gore o nne le seabe mo tiragalong e.

~38 km north-east of Concordia and 56km south-west of Aggeneys, Nama Khoi Local Municipality within the Namakwa District Municipality
Final Report
Renewable Energy
June 2026
Ummbila Emoyeni Five Wind Energy Facility, Mpumalanga

Scoping & EIA

Ummbila Emoyeni Five (Pty) Ltd is proposing the development of the Ummbila Emoyeni Five Wind Energy Facility (WEF), with a contracted capacity of up to 110MW, and associated grid connection infrastructure on a site near Morgenzon in the Lekwa Local Municipality within the greater Gert Sibande District Municipality, Mpumalanga. The project is planned to form part of the greater Ummbila Emoyeni WEF authorised under the Department of Forestry, Fisheries and the Environment (DFFE) (Ref. No. 14/12/16/3/3/2/2160). The Environmental Impact Assessment Report has been updated, as applicable, and submitted to the DFFE for decision-making.

Morgenzon, Lekwa Local Municipality within the Gert Sibande District Municipality
Final EIA Report
Renewable Energy
May 2026
Ummbila Emoyeni Four Wind Energy Facility, Mpumalanga

Amendment

Ummbila Emoyeni Cluster (Pty) Ltd is proposing amendments to the approved Ummbila Emoyeni Four Wind Energy Facility (WEF), with a contracted capacity of up to 140MW, and associated grid connection infrastructure on a site near Morgenzon in the Lekwa Local Municipality within the greater Gert Sibande District Municipality, Mpumalanga. The project forms part of the greater Ummbila Emoyeni WEF authorised under the Department of Forestry, Fisheries and the Environment (DFFE) (Ref. No. 14/12/16/3/3/2/2160). The Revised EMPr and Layout is available for a 30-day review and comment period. Register your interest to become involved in the process.

Morgenzon, Lekwa Local Municipality within the Gert Sibande District Municipality
Final EMPrs & Layout
Renewable Energy
January 2024
Upilanga Solar and Green Hydrogen Park, Northern Cape

Scoping & EIA

Emvelo Energia Proprietary Limited ("Emvelo"), proposes the development of Upilanga Solar and Green Hydrogen Park ("Upilanga Valley"), a strategic integrated baseload-dispatchable solar and green hydrogen infrastructure project (to be developed in phases), as well as associated infrastructure. The Background Information Document, providing details of the project and how to become involved in the process is available for download below. Register your interest to become involved in the process. Registreer u belangstelling om by die proses betrokke te raak. Kwadisa kgatlhegelo ya gago gore o nne le seabe mo tiragalong e.

~20km east of Upington at Karoshoek near the township of Karos, Dawid Kruiper Municipality (DKM) in the ZF Mgcawu (ZFM) District Municipality
Invitation to Register
Renewable Energy
February 2026
Watt Solar PV Facility, Gauteng

Amendment

Watt Solar PV (Pty) Ltd is applying to the Gauteng Department of Environment for an amendment to the existing Environmental Authorisation for the Watt Solar PV Facility. The amendment includes minor micro-siting to project infrastructure and a limited increase in the width of sections of the internal access roads, all within the previously authorised development area. The Motivation Report has been finalised and submitted to the Gauteng Department of Environment (GDEnv).

~10km southwest of Brakpan, City of Ekurhuleni Metropolitan Municipality.
Final Report
Renewable Energy
February 2026
Witpoortjie Solar PV Facility, Gauteng

Amendment

Watt Solar PV (Pty) Ltd is applying to the Gauteng Department of Environment for an amendment to the existing Environmental Authorisation for the Witpoortjie Solar PV Facility. The amendment includes the transfer of rights and obligations to Watt Solar PV (Pty) Ltd, as well as minor micro-siting to project infrastructure and a limited increase in the width of sections of the internal access roads, all within the previously authorised development area. The Motivation Report has been finalised and submitted to the Gauteng Department of Environment (GDEnv).

~10km southwest of Brakpan, City of Ekurhuleni Metropolitan Municipality
Final Report
Renewable Energy
May 2026
Zeus Substation Expansion, Mpumalanga

Basic Assessment

National Transmission Company South Africa (SOC) Ltd proposes to expand the footprint of the existing Zeus Substation by approximately 5ha to accommodate the installation of a 3rd 2000 MVA 765/400 kV transformer, extension of the 765kV busbar, equipping of 1x765 kV transformer bay, and 1x 400 kV transformer bay. This expansion will increase transmission capacity, strengthen the reliability of the electricity network, facilitate the integration of renewable energy in Mpumalanga, and improve power transfer capacity in the Cape corridor. The Basic Assessment Report has been finalised and submitted to the Department of Forestry, Fisheries and the Environment (DFFE).

~10 km south-west of Charl Cilliers, on Portion 20 of the Farm Vlakfontein 328, within the Govan Mbeki Local Municipality
Final Report
Grid Infrastructure